PROJECT: Aberdeen Village
CONTRACT:  $1.5 million
OWNER: Presbyterian Manors of Mid-America Inc.
ARCHITECT: Gould Evans Goodman Associates, PC
210,000 sq. ft. independent living, assisted living and skilled care retirement facility. Roof top and split system HVAC equipment, including full service kitchen.

PROJECT: Allied Signal CAS 2000 - Corporate Headquarters
CONTRACT;  $4.5 million
OWNER: Allied Signal
ARCHITECT: C.L. Architects
Corporate offices and production facility consisting of 550,000 sq. ft. for Commercial Avionics and Aerospace Division. Laminar flow stations, laboratory hood and electronic production line installations.


PROJECT: Arabia Riverboat Museum
CONTRACT:  $560,000
OWNER: Historic Constructors
ARCHITECT: Duncan Architects
Museum exhibit area and retail space, HVAC system consists of chilled weather AHUs, humidification and dehumidification controls, 35 degree F coolers and -10 degrees F freezers

PROJECT: Aries Power Plant
CONTRACT:  $2.7 million
OWNER: MEP Pleasant Hill, LLV
ARCHITECT: Black & Veatch
Office, warehouse, water treatment and electrical equipment facilities, HVAC is a rooftop unit with multiple zone VAV, multiple split systems and thermostatically controlled exhaust fans.

PROJECT: Bishop Spencer Place
CONTRACT: $5.2 million
OWNER: Bishop Spencer Place
ARCHITECT: B.N.I.M Architects
Retirement center with 60 independent living units, 30 assisted living units and a 60-bed nurse care unit. HVAC system is a split system heat pumps central exhaust system, and commercial kitchen exhaust/make up.

PROJECT: Black & Veatch Headquarters
CONTRACT:  $851,000
OWNER: Executive Hills Inc.
ARCHITECT: Black & Veatch
Four story building with 120,000 sq. ft. of office space with 300 ton central plant with hot water heating system and ammonia piping for blueprint machinery.

PROJECT: Briarcliff
CONTRACT:  $200,911
OWNER: Briarcliff Development Co.
ARCHITECT: Rees Masilionis Turly Architecture
35,000 sq. ft, four-story office building with 110 ton VAV packaged rooftop unit with DDC controls.

PROJECT: Cheleplis Office Building
CONTRACT:  $221,970
OWNER: Cheleplis Associates Inc.
ARCHITECT: Davidson Design Group
30,000 sq. ft., two-story office building with 120 ton packaged VAV rooftop units

PROJECT: Claridge Court
CONTRACT:  $1.3 million
OWNER: Life Care Retirement Communities Inc.
ARCHITECT; B.N.I.M. Architects
135-unit retirement center with three-story clubhouse and nursing center. HVAC system is water source heat pump loop with central plant, centralized laundry and kitchen.

PROJECT: Colgate Palmolive
CONTRACT:  $563,769
OWNER: Colgate Palmolive Co.
ENGINEER:  Albert Kahn Associates Inc.
Mechanical modifications for third floor addition to building, which include high pressure steam piping, low-pressure stem piping, chilled and hot water piping, air handling unit installation and ductwork modifications.

 
PROJECT: Cook Composites & Polymers
CONTRACT;  $500,900
OWNER: Cook Composites 7 Polymers
ARCHITECT; Fred Truog & Associates
Second level conversion of warehouse space to office/laboratory includes 14 constant volume fume hood installation with associated HVAC systems.

PROJECT: Cook, Composites and Polymers Laboratory Building #51
CONTRACT:  $1.5 million
OWNER: Cook Composites and Polymers
ARCHITECT; Fred Truog & Associates
Complete renovation of five story, 65,000 sq. ft. corporate office building and laboratory listed on historic register. HVAC system consists of new chilled water system and hot water heating system, variable air volume system with hot water reheat, six packaged air handling units, one per floor, 22 fume hoods with heat recovery and variable air volume supply and exhaust systems. Laboratory system consists of Phoenix laboratory controls with make up air, exhaust air and supply air valves interconnected to modulate as required based on fume hood sash position. heat pipe type air-to-air heater exchanger recovers energy from lab exhaust air.

PROJECT: Colorado Kenworth
CONTRACT:  $711,713
OWNER: Midwest Holding Co.
ARCHITECT: Finkle/Williams
131,500 sq. ft. truck sales and service facility with office rooftop VAV system, maintenance bay evaporative cooling and vehicle exhaust systems.

PROJECT: Cooper's Animal Health - Bldg. 55 Expansion
CONTRACT:  $250,000
OWNER: Cooper's Animal Health
ARCHITECT: Blom & Associates
Expansion of research and development facility while maintaining ongoing R&D in existing building. System includes new air handling units, chillers, pumps and HEPA filtration, addition of two incubator areas with close control of both temperature and humidity.

PROJECT: eScout.com
CONTRACT;  $193,064
OWNER: eScout.com
ARCHITECT: Bell/Knott Associates
20,500 sq. ft. renovation for banking e-commerce clients with conversion of a light industrial constant volume air delivery system to a variable air volume system.

PROJECT: Embassy Suites Hotel-Kansas City
CONTRACT: $1.4 million
OWNER: John Q. Hammons
ARCHITECT: Hood-Rich Associates
Hotel with 280 guest rooms, plus restaurant and convention facility, with four pipe hot/chilled water system with 470 ton central chilled water plant.

PROJECT: Excel Communications
CONTRACT:  $223,700
OWNER: Excel Communications
ARCHITECT: Carr Blunt Newmark
11,875 sq. ft. raised floor data processing/switching station for communication clients, 121 tons of air-cooled Liebert computer room HVAC equipment with humidity control.

PROJECT: Executive Hills South - Bldg. 40
CONTRACT:  $879,536
OWNER: Executive Hills Inc.
ARCHITECT: P.B.N.I.
Fifteen story building with 240,000 sq. ft. commercial office space and 640 ton chilled water central plant. Air handling system is a built up variable air volume penthouse air handling unit.

PROJECT: Frontier Junior High School
CONTRACT:  $597,545
OWNER: Olathe Public School District
ARCHITECT: Hollis & Miller
Interconnected buildings with 84,961 sq. ft. of classroom space and 27,154 sq. ft. of non-educational space, including natatorium, gymnasium and kitchen/cafeteria. Other systems include dust collection for woodwork shop and welding exhaust hood for metal shop. Heating and air conditioning system includes 62 water source heat pump loop systems with a 300 ton cooling tower and two boilers for backup heat.

PROJECT; The Gardens
CONTRACT:  $331,051
OWNER: Gardens
ARCHITECT: The Lawrence Group Architects
85,000 sq. ft. independent living assisted living and skilled care retirement facility, rooftop and split system HVAC equipment including full-service kitchen

PROJECT: Garmin New Office and Production Facility
CONTRACT:  $607,945
OWNER: Garmin International Inc.
ARCHITECT: George Butler Associates Inc.
HVAC is 300 tons of variable volume rooftop heating and cooling in office and warehouse, controlled by a direct digital control system, project also includes humidification as well as compressed air and nitrogen piping for processes.

PROJECT: Internal Medicine Department
CONTRACT:  $111,560
OWNER: North Kansas City Hospital
Variable air volume system with hot water reheat and DDC controls with replacement of heating water pump in central plant and heating water risers throughout the building.

 
PROJECT: Jack Henry
CONTRACT:  $1.9 million
OWNER: Jack Henry & Associates
ARCHITECT: The Casey Associates
Data processing centers located in Lenexa, Kan., Miami, Fla, and Houston, Texas (combined sq. ft, 124,000) HVAC is chilled and hot water and VAV rooftop units with underfloor air delivery system.

PROJECT: Johnson County Community College - Classroom/Laboratory Building
CONTRACT:  $551,650
OWNER: Johnson County Community college
ARCHITECT: Peckham Guyton Albers Viets
Four story classroom/laboratory building with a built up VAV chilled water air handling unit, chilled water supplied from campus loop, variable air volume terminals and laboratory exhaust system.

PROJECT: KCPT
CONTRACT:  $548,010
OWNER: KCPT
ARCHITECT: Gastinger Walker Harden Architects
Office and television studio remodel that includes five rooftop units with VAV boxes, built in place AHUs, DX split system units, hot water baseboard unit heaters and complete DDC control system.

PROJECT: Kingswood Manor
CONTRACT:  $204,776
OWNER: Kingswood Manor
ARCHITECT: George Butler Associates
19,500 sq. ft. renovation and addition to retirement facility includes extension of four pipe hot and chilled water system to vertical resident FCUs, also includes administration office renovation.

PROJECT: Knight Ridder Commodity News
CONTRACT:  $1.1 million
OWNER: Executive Hills Inc.
ARCHITECT: Ellerbe Beckett
Main plant consists of a mammoth penthouse unity, 260 ton variable air volume cooling system with electric heat, medium and low pressure insulated duct system in addition to six Liebert computer room air conditioning units with a total capacity of approximately 150 tons.

PROJECT: Leavenworth West Middle School
CONTRACT:  $238,957
OWNER: Leavenworth Public School District
ARCHITECT: Viron
Rooftop unit replacements with 165 tons of air conditioning with gas heat and ductwork modifications.

 
PROJECT: Leawood City Hall
CONTRACT:  $257,450
OWNER: City of Leawood, Kansas
ARCHITECT: Abend-Singleton Associates
Three story, 35,000 sq. ft. building with 93 tons of rooftop cooling, VAV system with hot water heating system.

PROJECT: Lee's Summit High School
CONTRACT:  $953,445
OWNER: Reorganized School District No. 7 of Jackson County, Mo.
ARCHITECT: Hollis & Miller
Replacement of windows with EIFS system and aluminum windows, replacement of two fire tube steam boilers, pumps and accessories, and major piping modifications, addition of 250 ton air cooled chiller and three air handling units.

PROJECT; Lenexa National Guard Armory
CONTRACT:  $279,063
OWNER: State of Kansas/City of Lenexa
ARCHITECT: Hansen Midgley Niemackl Architects
One story, 28,000 sq. ft. building with gymnasium that also serves as a multi-purpose armory/recreation center with 52 tons of DX air conditioning and hot water heating system.

PROJECT: Level 3 Communications
CONTRACT:  $507,000
OWNER: Level 3 Communications
New tenant improvement for fiber optic communication switching station, 98 tons, raised floor computer room air conditioning system, interior glycol cooled Liebert air handling units with remote dry coolers.

PROJECT; Livestock Exchange Building
CONTRACT:  $658,000
OWNER: National Farms Inc.
ARCHITECT: B.N.I.M. Architects
Renovation of 250,000 sq. ft. office building using a water source heat pump system. Condenser water loop is an 8-inch high pressure steam reducing station, hot water converter and 400 ton cooling tower controlled by an Environmental Mechanicals control system.

PROJECT: Marriott Blue Springs
CONTRACT:  $475,348
OWNER: Southern States Development
ARCHITECT; Michael Treanor
69,000 sq. ft., 126 room residence inn, 92 tons of unitary packaged through the wall and rooftop HVAC equipment.